Whoa, progress!

It was less than a month ago that we first noticed movement at 19th and Catharine Sts. for the first time in years. When we last checked in, the builders were preparing to pour the foundations for the five houses fronting Dorrance St. We were assuming at that time that they would complete those houses and sell them before constructing the other five in the development. It seems we were wrong. All of the first five houses are currently framed to at least the first floor, and footers are currently in place for the second five. Figure foundations will be poured next week.

Future houses fronting 19th St.

Moving along on Dorrance St.

At this rate, we should have ten new homes at this site any minute. Oh wait, with the hurricane coming maybe it’ll be a few months instead. Whoops.